Who should Apply?
Any person or organization that wants to put up a building, transform an existing building, demolition an existing structure.
(Contact the Works Department, the Physical Planning Department offices, relevant agencies or consultants for advice and assistance)
Applicants Requiring Permission In Principle (AIP)
Three (3) sets of sketch drawings
Three (3) copies of brief outline of project covering the location, design, activities and operational characteristics.
Evidence of Neighborhood consultation and comments
Applications seeking change of use of an existing permit
Previous permit on existing building
Proposed amendments to drawings if relevant
Evidence of Neighborhood consultation and comments for the new use of premises
Validation of Development and Building Permit
Development and Building permits are valid for five years.
Applicants who are unable to complete developments within permit validity period are required to seek permit for Extension of Time.
Application for Extension to existing Building should comprise;
Previous permit on existing building
Four (4) new copies of block and site plan to scale of 1/20 or 1/40 showing the position of the building(s) and other works on site.
Purchase of Forms
Buy building permit application form and PPD form 1 from the Works Departments and Physical Planning Department office
Completion of Forms
Complete in full, both the Building Permit Application Form and the PPD Form 1. (Where you have difficulty in completing the forms contact Works Departments & Physical Planning Department offices for advice and assistance)
Submission
Submit completed forms with all other attachments as specified in the Building Permit Application and PPD form1 to the Physical Planning Department office.
(Contact officer in charge to be informed of corrections to be made or additions if any, the processing fee, date for inspection of site etc)
Site Inspection
By a team from Physical Planning Department
and works department
Technical sub-committee
Application is vetted by officers from various institutions
Comment compiled and forwarded to applicants if any
Recommendation to Spatial Planning Committee for decision
Endorsing of permit and collection by applicant
Finally the Works Department shall inspect the facility upon completion and grant a certificate of habitation
Collection of Permit
Pay approved building permit fee to the Works Department on receipt of approval letter.
Collect building permit and seek further instructions for commencement of building project from Works Department.
Difference between the Development Permit and Building Permit
Development permit is issued by the Physical Planning Department for the developer to enter the land for the needed preparation
Building Permit is issued by the Works Department for the developer to start construction
Challenges
Cooperation between the various agencies and departments and understanding and appreciation of each ones role
Development preceding planning
Land use disorder, slums and squatter settlements
Limited data and information
Increasing environmental deterioration
Monitoring the construction process
It is important to note that the validity of a Building Permit issued in accordance with the above process is five (5) years after which a new permit must be sought.
Developers are therefore required to seek renewal of Building Permit if development is not completed within five (5) years.
Development Permit Application Process Flow Chart